Civilization101Blueprint

Steel frame and reinforced concrete

Build frames of reinforced concrete or steel, or confined masonry, that carry their loads with the steel where the tension is, the concrete mix, cover and curing the exposure needs, and the earthquake detailing the region needs, each stage inspected before it is hidden.

Tier 5 · Second industrial revolution Shelter t5-concrete Blocked by prerequisites
Reinforcing bars laid in mats across a bridge deck before the pour, CSVT River Bridge, Pennsylvania (2020); a gantry robot ties the crossings, and every bar is set on chairs to hold its cover. TyBot at CSVT River Bridge · Taken on 10 January 2020 · BryceNelson7 · CC BY-SA 4.0 · Commons ↗

Everything for this step

Field guide
Engineering → 7 sections
Builds
None yet.
Reference sheets
None.
Sciences it rests on
Engineering · Physics · Chemistry
Track
Dwellings, level 5 of 5

Why this matters

Concrete resists compression and cracks under tension: India's concrete code estimates its flexural strength at 0.7 √fck, about 3.5 N/mm² for concrete of 25 N/mm² (IS 456). So every beam, slab and column carries steel bars where the tension is, wrapped in enough dense concrete to keep the steel from rusting.

What brings these buildings down is rarely the calculation. On 24 April 2013 the Rana Plaza building near Dhaka collapsed and killed more than 1,100 people (ILO): its upper floors had been added illegally to house factories and heavy generators that shook the building, and the day after large cracks appeared, workers were ordered back inside (University of Texas case study). Design by a trained engineer to a published code; this step teaches what to check.

The shape of it

  1. Build only to an engineer's design and a published code, and add no storey, generator or heavy machine without a new structural check.
  2. Choose the mix by exposure: in mild exposure at least 300 kg of cement per m³, water/cement 0.55 at most and grade M20; in severe exposure 320 kg, 0.45 and M30 (IS 456).
  3. Check every batch's slump, 25–75 mm for lightly and 50–100 mm for heavily reinforced members, and never add water at the pour.
  4. Keep the concrete damp for at least 7 days and crush 150 mm cubes at 7 and 28 days; the grade is the 28-day strength.
  5. Hold the cover: 20 mm in mild exposure to 75 mm in extreme, 50 mm in footings, on spacers.
  6. In earthquake zones, confine the joints: 135° hooks, hoops 75–100 mm apart near every beam–column joint, laps only in the middle half of a column.
  7. Protect steel frames from fire: steel keeps only about 60 % of its yield strength at 550 °C.
  8. Inspect the bars before every pour and stop work at the first structural crack.
Detailing a column and beam joint for earthquakes Fig 1
Column hoops at 75–100 mm (at most a quarter of its width) over l₀ — at least the column depth, a sixth of the clear height and 450 mm — at each joint; column bars lapped only in the middle half; beam hoops at d/4 or 8 bar diameters (not closer than 100 mm) for 2d from the column, the first within 50 mm of it; every tie bent 135° with an extension of 10 bar diameters, at least 75 mm, into the core (IS 13920). Not to scale.

Doing it, step by step

The summary above says what has to happen. This says how, with the numbers that decide whether it works.

1 · Design to a code, and let the code keep the building

Reinforced concrete and steel frames are designed by calculation, by a trained engineer, to a published code: the loads each floor will carry, the size of every member and every bar. Free codes a reader can hold offline include India's IS 456 for concrete and IS 13920 for earthquake detailing.

  • A building permit fixes the number of storeys and the use. Use changes nothing without a new check: a floor of offices is not a floor of looms.
  • An inspector checks the work at each stage that will be hidden: footings, bars before each pour, and the finished frame.
  • A crack in a column, beam or wall that was not there yesterday stops work and empties the building until an engineer has seen it.
At Rana Plaza in 2013 large cracks appeared the day before the collapse, and workers were sent back in the next morning; more than 1,100 died.
✓ Check: The building has a design to a named code, a permit giving its storeys and use, and an inspection record for every pour.

2 · Choose the mix by what the concrete will face

Less water makes stronger, denser concrete. IS 456 (Table 5) sets limits for reinforced concrete by exposure:

  • Mild (protected indoors): at least 300 kg of cement per m³, free water/cement ratio at most 0.55, grade at least M20.
  • Moderate (sheltered from severe rain, or buried in non-aggressive soil): 300 kg, 0.50, M25.
  • Severe (severe rain, wetting and drying, coastal air): 320 kg, 0.45, M30.
  • Very severe (sea spray, corrosive fumes): 340 kg, 0.45, M35; extreme (tidal zone, aggressive ground): 360 kg, 0.40, M40.

The grade number is the strength in N/mm² of a 150 mm cube at 28 days: M25 crushes at 25. Use clean, graded aggregate and drinkable water; batch by weight, not by shovel.

✓ Check: The mix sheet names the exposure class and meets that row's cement content, water/cement ratio and grade.

3 · Test the slump, place and compact

The slump test measures workability: fill the standard cone (300 mm high, 200 mm across the base, 100 mm at the top) in four equal layers, tamp each with 25 strokes of a 16 mm rod, lift the cone and measure how far the concrete sinks (IS 1199). IS 456 asks for:

  • 25–75 mm for lightly reinforced slabs, beams, walls and columns, floors and strip footings.
  • 50–100 mm for heavily reinforced sections.
  • 75–100 mm for pumped concrete.

Never add water to a batch that is too stiff: reject it or have the plant adjust the next one. Place the concrete within the time the mix allows, in layers, and compact each with a poker vibrator until air stops rising; do not drop it from a height that separates the stone.

Measuring a slump test (2016): the emptied cone stands upside down beside the concrete, and the drop from its top is read with a rule laid across it. Essais sur béton DSC 2170 · 2016-03-17 10:20:46 · Habib M’henni · CC BY 4.0 · Commons ↗
✓ Check: Every batch has a recorded slump inside the range for its member, and no water was added at the pour.

4 · Cure it for seven days, then crush the cubes

Concrete gains strength only while it stays damp. Keep exposed surfaces continuously wet, under ponded water or wet sacking, for at least 7 days after placing when made with ordinary Portland cement (IS 456, 13.5.1); longer in hot, dry or windy weather.

Cast cubes from the same batches: 150 mm steel moulds, cured in water, crushed at 7 and 28 days. The 28-day result must reach the grade. A low result means coring the member or loading it only after an engineer's check.

Concrete test cubes curing under water in buckets (2021), kept wet until they are crushed at 7 and 28 days. Cube Test 2 · 30 July 2021 (according to Exi · Fotokannan · CC BY-SA 4.0 · Commons ↗
A compression testing machine (2016): a cube is crushed between its platens and the dials record the load at failure. Concrete test device · 2016-10-19 11:25:09 · Mohammad Hijjawi · CC BY-SA 4.0 · Commons ↗
✓ Check: The curing log shows each pour kept wet for 7 days or more, and each set of cubes reached its grade at 28 days.

5 · Place the steel: grade, cover, laps and ties

Use deformed bars of a known grade (Fe 415 or Fe 500 in IS 456: yield strength 415 or 500 N/mm²), clean of loose rust and oil, bent cold to the drawing.

Cover — the concrete between the bar and the surface — keeps out water, air and chloride (IS 456, Table 16):

  • 20 mm mild, 30 mm moderate, 45 mm severe, 50 mm very severe, 75 mm extreme exposure; at least 50 mm in footings.
  • Hold it with concrete or plastic spacers and chairs, never stones or offcuts of wood.

Laps: a bar in flexural tension laps its development length and at least 30 bar diameters; in direct tension, twice the development length; in compression, at least 24 diameters. Stirrups in beams no farther apart than 0.75 d (d = effective depth) or 300 mm; column ties no farther apart than the column's least width, 16 bar diameters or 300 mm.

✓ Check: Before the pour, a tape on the cage shows cover, laps and stirrup and tie spacing all inside the drawing's figures, and every spacer is in place.

6 · Detail every joint for earthquakes

In an earthquake the joints are where frames fail, so the steel there is closer and better anchored (IS 13920, 1993; its 2016 revision and other current codes are at least as strict):

  • Hooks: every hoop and tie ends in a 135° hook with an extension of 10 bar diameters, and at least 75 mm, that wraps into the core. A 90° end opens under shaking.
  • Beam ends: over twice the depth from each column face, hoops at no more than d/4 or 8 bar diameters (but not closer than 100 mm), the first within 50 mm of the face.
  • Columns: from each joint, over the greatest of the column's larger dimension, a sixth of its clear height and 450 mm, hoops at no more than a quarter of its least width, 75–100 mm apart, continuing 300 mm into the footing. Lap column bars only in the middle half of the height.
  • Minimum column width 200 mm, and 300 mm where beams span more than 5 m or columns stand more than 4 m unbraced.
  • No soft storey: a storey much more open or flexible than the one above, such as an open ground floor under walled flats, gets confining steel over the full height of its columns, and an engineer's check.
Never cut, drill or chase a column or beam to pass a pipe or cable without the engineer's approval: it removes the steel or the cover the design relies on.
✓ Check: Every hoop on the cage has 135° hooks with their extensions, and the close-spaced zone at each joint measures at least the length above.

7 · Or build confined masonry for low-rise houses

For one- and two-storey buildings, confined masonry — walls laid first, then small reinforced-concrete tie-columns and tie-beams cast against them — performs well in earthquakes with far less steel than a frame (EERI and IAEE guide, 2011):

  • Tie-columns at every wall end and intersection, no more than 4.5 m apart in regions of high seismicity and 6 m in moderate.
  • A tie-beam along the top of every wall, at most 3 m up.
  • Ties of at least 6 mm bar with 135° hooks, no more than 200 mm apart, halved near the tie-column ends in high seismicity; longitudinal laps at least 40 bar diameters; 20 mm cover to the ties.
  • Walls at least 110 mm thick and no more than 3 m high.
  • Enough wall in each direction: buildings that collapsed had walls of less than 1 % of the floor area in one direction; the guide's table gives the minimum for each hazard, soil and storey count.
✓ Check: On the plan, no wall panel is longer than the tie-column spacing for the region, every wall has a tie-beam on top, and the wall area in each direction meets the guide's table.

8 · Steel frames: graded steel, graded bolts, fire protection

Use hot-rolled sections of a stated grade, such as S275 or S355 (the number is the yield strength in N/mm²), joined by graded bolts tightened to the design. A steel frame is quick and light, and it loses strength in fire: loss begins at about 300 °C, quickens above 400 °C, and by 550 °C steel keeps about 60 % of its room-temperature yield strength and 45 % of its stiffness (SteelConstruction.info).

  • Protect every load-bearing member to the fire resistance the building code asks: concrete or masonry encasement, fire boards or intumescent paint.
  • After a fire, have every member and connection assessed; bolts heated above about 450 °C lose strength, and replacing them is the cautious course.
Steel roof beams coated with sprayed fire protection (2018), which keeps the steel below the temperature at which it loses its strength. Travi acciaio con protezione fuoco · 2018-02-08 11:11:03 · A7N8X · CC BY-SA 4.0 · Commons ↗
✓ Check: Every load-bearing steel member carries its specified fire protection, and the bolt grade and tightening are recorded for every connection.

9 · Inspect what will be hidden, and keep the load within the design

Concrete hides its mistakes, so inspect at the stages that cannot be seen later:

  1. Excavation and footing bars before the footing is cast.
  2. Column and wall cages, and beam and slab bars, before every pour: bar sizes, count, cover, laps, hooks and spacers against the drawing.
  3. Formwork and props before the pour, and striking only when the concrete has the strength.
  4. The finished frame before walls and finishes cover it.

Write each inspection down and sign it. Afterwards, the building's own record — its design loads, storeys and use — goes with it to every owner; any change goes back to an engineer.

✓ Check: A signed record exists for each of the four stages, and the building's present use, storeys and heavy equipment match its design.

How this fails

Floors, factories or generators added to a building designed for less, as at Rana Plaza in 2013.
Water added at the pour to make the mix flow: every extra litre weakens it and opens it to rust.
Bars sitting on the formwork with no spacers, so the cover is a few millimetres and the steel rusts and splits the concrete.
Hoops with 90° ends, widely spaced at the joints, which open in an earthquake and let the column's bars buckle.
An open ground floor under walled storeys, where the earthquake's movement concentrates and the columns fail.
Unprotected steel columns in a fire, or bolts reused after one.

How you know it worked

VerificationEvery pour has a signed inspection of the bars, cover and laps against the drawing, every batch's slump and every set of cubes is logged and meets its grade at 28 days, and the building carries no load or storey the design did not allow for.